Submit the Planned Public Improvement Summary (WH-118) to BOLI prior to each budget period.
Include the prevailing wage rates, public works bond requirement and other required language in the contract and the contract specifications.
Submit the PWR fee and Public Works Fee Information form (WH-39) to BOLI for every public works contract awarded.
Submit the Notice of Public Works form (WH-81) and copy of the disclosure of first-tier subcontractors to BOLI within 30 days of awarding the contract.
Confirm that the correct prevailing wage rates and the details of any benefit plans are conspicuously posted on the project site.
Verify that all contractors and subcontractors are using the correct work classifications.
Confirm that all contractors and subcontractors are filing complete and accurate certified payrolls, and are paying employees the correct prevailing wage rate.